For a weatherproof transition between these roof types, implement these critical steps:
 
	Structural Connection:
 
		Install double 2x ledger board on main house with 1/2" galvanized through-bolts (spaced 16" OC)
	
	
		Use Simpson H1 hurricane ties at rafter connections
	
	Water Management:
 
		Step flashing must extend 12" up pitched roof under shingles
	
	
		Saddle flashing over flat roof membrane (minimum 24-gauge galvanized)
	
	
		Slope flat roof 1/4" per foot toward scupper drain
	
	Material Transitions:
 
		Ice/water shield over entire flat roof deck + 3' up pitched roof
	
	
		EPDM or TPO membrane for flat section with termination bar at pitch transition
	
	Climate Consideration: In freeze-thaw regions, add heating cable in gutter above transition to prevent ice dam formation.